08-图8 How Long Does It Take

7-12 How Long Does It Take(25 分)

Given the relations of all the activities of a project, you are supposed to find the earliest completion time of the project.

Input Specification:

Each input file contains one test case. Each case starts with a line containing two positive integers N (100), the number of activity check points (hence it is assumed that the check points are numbered from 0 to N1), and M, the number of activities. Then M lines follow, each gives the description of an activity. For the i-th activity, three non-negative numbers are given: S[i]E[i], and L[i], where S[i] is the index of the starting check point, E[i] of the ending check point, and L[i] the lasting time of the activity. The numbers in a line are separated by a space.

Output Specification:

For each test case, if the scheduling is possible, print in a line its earliest completion time; or simply output "Impossible".

Sample Input 1:

9 12
0 1 6
0 2 4
0 3 5
1 4 1
2 4 1
3 5 2
5 4 0
4 6 9
4 7 7
5 7 4
6 8 2
7 8 4

Sample Output 1:

18

Sample Input 2:

4 5
0 1 1
0 2 2
2 1 3
1 3 4
3 2 5

Sample Output 2:

Impossible


#include
#include
using namespace std;
const int maxn=105,infinity=10000;
int N,M,minTime[maxn] = {0},InDegree[maxn] = {0},TopNum[maxn] = {0},G[maxn][maxn] = {0};
void ToplogicSort(){
    int v,mark = 1,cnt = 0;
    queueq;
    for(int i=0;i maxT) maxT = minTime[i];
        }
        cout<>N>>M;
    for(int i=0;i>a>>b>>l;
        InDegree[b]++;
        G[a][b] = l;
    }
    ToplogicSort();

    return 0;
}