A work breakdown structure (WBS) in project management and systems engineering, is a tool used to define and group a project's discrete work elements (or tasks) in a way that helps organize and define the total work scope of the project[1].
A work breakdown structure element may be a product, data, a service, or any combination. A WBS also provides the necessary framework for detailed cost estimating and control along with providing guidance for schedule development and control. Additionally the WBS is a dynamic tool and can be revised and updated as needed by the project manager.[1]
The Work Breakdown Structure is a tree structure, which shows a subdivision of effort required to achieve an objective; for example a program, project, and contract. In a project or contract, the WBS is developed by starting with[2] :
Overview
The Work Breakdown Structure provides a common framework for the natural development of the overall planning and control of a contract and is the basis for dividing work into definable increments from which the statement of work can be developed and technical, schedule, cost, and labor hour reporting can be established.[2]
A work breakdown structure permits summing of subordinate costs for tasks, materials, etc., into their successively higher level “parent” tasks, materials, etc. For each element of the work breakdown structure, a description of the task to be performed is generated. [3] This technique (sometimes called a System Breakdown Structure [4]) is used to define and organize the total scope of a project.
The WBS is organized around the primary products of the project (or planned outcomes) instead of the work needed to produce the products (planned actions). Since the planned outcomes are the desired ends of the project, they form a relatively stable set of categories in which the costs of the planned actions needed to achieve them can be collected. A well-designed WBS makes it easy to assign each project activity to one and only one terminal element of the WBS. In addition to its function in cost accounting, the WBS also helps map requirements from one level of system specification to another, for example a requirements cross reference matrix mapping functional requirements to high level or low level design documents.
The concept of Work Breakdown Structure developed with the Program Evaluation and Review Technique (PERT) in the United States Department of Defense (DoD). PERT was introduced by the U.S. Navy in 1957 to support the development of its Polaris missile program. [1] While the term "work breakdown structure" was not used, this first implementation of PERT did organize the tasks into product-oriented categories.[5]
By June 1962, DoD, NASA and the aerospace industry published a document for the PERT/COST system which described the WBS approach. [6] This guide was endorsed by the Secretary of Defense for adoption by all services.[7] In 1968, the DoD issued "Work Breakdown Structures for Defense Materiel Items" (MIL-STD-881), a military standard requiring the use of work breakdown structures across the DoD. [8] This standard established top-level templates for common defense materiel items along with associated descriptions (WBS dictionary) for their elements.
The document has been revised several times, most recently in 2005. The current version of this document can be found in "Work Breakdown Structures for Defense Materiel Items" (MIL-HDBK-881A).[9] It includes instructions for preparing work breakdown structures, templates for the top three levels of typical systems, and a set of "common elements" that are applicable to all major systems and subsystems.
Defense Material Item categories from MIL-HDBK-881A:
The common elements identified in MIL-HDBK-881A, Appendix I are: Integration, assembly, test, and checkout; Systems engineering; Program management; Training; Data; System test and evaluation; Peculiar support equipment; Common support equipment; Operational and site activation; Industrial facilities; and Initial spares and repair parts
In 1987, the Project Management Institute (PMI) documented the expansion of these techniques across non-defense organizations. The Project Management Body of Knowledge (PMBOK) Guide provides an overview of the WBS concept, while the "Practice Standard for Work Breakdown Structures" is comparable to the DoD handbook, but is intended for more general application.[11]
|
This section contains too much jargon and may need simplification or further explanation. Please discuss this issue on the talk page, and/or remove or explain jargon terms used in the article. Editing help is available. (September 2008) |
One of the most important Work Breakdown Structure design principles is called the 100% Rule [12]. It has been defined as follows:
Mutually exclusive: In addition to the 100% Rule, it is important that there is no overlap in scope definition between two elements of a Work Breakdown Structure. This ambiguity could result in duplicated work or mis-communications about responsibility and authority. Likewise, such overlap is likely to cause confusion regarding project cost accounting. If the WBS element names are ambiguous, a WBS dictionary can help clarify the distinctions between WBS elements. The WBS Dictionary describes each component of the WBS with milestones, deliverables, activities, scope, and sometimes dates, resources, costs, quality.
If the Work Breakdown Structure designer attempts to capture any action-oriented details in the WBS, he/she will likely include either too many actions or too few actions. Too many actions will exceed 100% of the parent's scope and too few will fall short of 100% of the parent's scope. The best way to adhere to the 100% Rule is to define WBS elements in terms of outcomes or results. This also ensures that the WBS is not overly prescriptive of methods, allowing for greater ingenuity and creative thinking on the part of the project participants. For new product development projects, the most common technique to ensure an outcome-oriented WBS is to use a product breakdown structure. Feature-driven software projects may use a similar technique which is to employ a feature breakdown structure. When a project provides professional services, a common technique is to capture all planned deliverables to create a deliverable-oriented WBS. Work breakdown structures that subdivide work by project phases (e.g. Preliminary Design Phase, Critical Design Phase) must ensure that phases are clearly separated by a deliverable also used in defining Entry and Exit Criteria (e.g. an approved Preliminary Design Review document, or an approved Critical Design Review document).
A question to be answered in determining the duration of activities necessary to produce a deliverable defined by the WBS is when to stop dividing work into smaller elements. There are several heuristics or "rules of thumb" used when determining the appropriate duration of an activity or group of activities necessary to produce a specific deliverable defined by the WBS.
A work package at the activity level is a task that:
It is common for Work Breakdown Structure elements to be numbered sequentially to reveal the hierarchical structure. For example 1.3.2 Rear Wheel identifies this item as a Level 3 WBS element, since there are three numbers separated by a decimal point. A coding scheme also helps WBS elements to be recognized in any written context.[14]
A terminal element is the lowest element (activity or deliverable) in a work breakdown structure; it is not further subdivided. Terminal elements are the items that are estimated in terms of resource requirements, budget and duration; linked by dependencies; and scheduled. A terminal element is sometimes called a work package, although the two terms are not synonymous.
The figure (on the right) shows a Work Breakdown Structure construction technique that demonstrates the 100% Rule and the "progressive elaboration" technique. At WBS Level 1 it shows 100 units of work as the total scope of a project to design and build a custom bicycle. At WBS Level 2, the 100 units are divided into seven elements. The number of units allocated to each element of work can be based on effort or cost; it is not an estimate of task duration.
The three largest elements of WBS Level 2 are further subdivided at Level 3. The two largest elements at Level 3 each represent only 17% of the total scope of the project. These larger elements could be further subdivided using the progressive elaboration technique described above.
WBS design can be supported by software (e.g. a spreadsheet) to allow automatic rolling up of point values. Estimates of effort or cost can be developed through discussions among project team members. This collaborative technique builds greater insight into scope definitions, underlying assumptions, and consensus regarding the level of granularity required to manage the project.