最近在《软件协同设计》课程中学习了WBS(Work Breakdown Structure)
工作结构分解方法,在此进行总结。
WBS:工作分解结构(Work Breakdown Structure), 创建WBS是把项目工作按阶段可交付成果分解成较小的,更易于管理的组成部分的过程。
WBS是项目管理重要的专业术语之一。WBS的基本定义 :以可交付成果为导向对项目要素进行的分组,它归纳和定义了项目的整个工作范围每下降一层代表对项目工作的更详细定义。无论在项目管理实践中,还是在PMP,IPMP考试中,工作分解结构(WBS)都是最重要的内容之一。WBS总是处于计划过程的中心,也是制定进度计划、资源需求、成本预算、风险管理计划和采购计划等的重要基础。WBS同时也是控制项目变更的重要基础。项目范围是由WBS定义的,所以WBS也是一个项目的综合工具。
如何创建WBS,Project management Insitute
出版的 《Practice Standard for Work Breakdown Structures》
中对WBS做了详细的描述。
网盘链接:https://pan.baidu.com/s/1PgecXzFi-6fMjaS0aBzeHw
密码: fehk
The Work Breakdown Structure (WBS) can be created new, or it can reuse com- ponents from other WBSs. When reusing existing components, WBS elements may be drawn from previous similar projects or from standard project templates that the organization has determined support accepted best practices.
The following sections in this chapter are presented as guides for use during the development of a WBS, and contain a number of topics for consideration:
Some of the sections can be used as checklists for the development and refine- ment of the WBS.
The WBS evolves through an iterative consideration of the project’s purpose and objectives, functional/performance design criteria, project scope, technical performance requirements, and other technical attributes. A high-level WBS can often be developed early in the conceptual stage of the project. Once the project is defined and specifications are prepared, a more detailed WBS can be developed.
The WBS can assist the project manager and stakeholders in developing a clear vision of the end product(s) of the project and of the overall process by which it will be created. With this in mind, the following should stimulate thought when developing a WBS to manage the project:
Have you formulated a vision of the final product in your mind?
These thoughts and questions are intended to help the project manager develop a clear statement of what the product of the project is—and to help answer the question, “How does one eat an elephant?” Answer: “One bite at a time!” The WBS is the technique for dividing “the elephant” into bite-sized pieces.
The following steps describe the general process for developing a WBS:
SOFTWARE IMPLEMENTATION PROJECT WBS
1.0 Project Management
2.0 Product Requirements
3.0 Detail Software Design
4.0 System Construction