Nework项目周报-(2018/04/02-2018/04/09)

Nework项目周报-(2018/04/02-2018/04/09)_第1张图片

本周4月5日至4月8日是中国清明节放假期间,Nework项目依然保持产品、UI、技术、运营等方面的进度推进,不断打磨迭代,力求提供更加完善的产品体验。以下为本周项目进度报告:

产品设计:

根据产品数据结构,收集整理地区、类目数据字典,完成度约50%;

Nework用户模块流程修正及优化,加入会员等级体系,完成度约70%;

优化用户体验,Nework产品信息结构改版,完成度约75%;

与技术开发团队紧密沟通,确保产品需求的落地执行;

UI设计:

Nework已完成PC端页面设计;

Nework用户模块移动端页面设计,完成度约35%;

技术研发:

Nework登录注册及用户模块前端开发,完成100%;

Newpay补充规则细节开发,完成度约20%;

系统测试:

接口测试用例编写,接口测试环境搭建,接口调试成功,完成100%;

功能性测试用例编写完成4个模块,完成100%;

市场运营:

Nework官方社群日常维护,收集、整理用户反馈的信息并及时进行处理;

筹划搭建NKC线上、线下支付应用场景并进行小范围测试,测试数据整理;

初步制定Nework产品上线前内测用户邀请规则,完成度30%;

April 5th to 8th is China Ching Ming Festival. The Nework project still keep pushing ahead on products, UI, technology, operations, etc. during the holidays, continuely optimizing and iterating to provide better product experience. The following is the weekly report of Nework for this week:

Product Design:

The collection of regional and category data dictionaries according to the product data structure has been completed by about 50%;

Optimized the Nework user module process, add the membership rating system, now has been completed by about 70%;

Optimized user experience, revised the Nework product information structure ,now has been completed by about 75%;

Keep close communication with the R&D team to ensure the implementation of product demands;

UI Design:

All pages on The PC-end has been completed;

Pages on mobile itermial has been completed by about 35%;

Technology Research & Development:

All front-end pages of login and registration and user module has been completed;

The developmentof added details rules of Newpay has been completed by about 20%;

System Test:

Interface test case preparation, interface test environment setup, interface debugging has been completed;

Four modules of functional test cases preparation has been completed;

Marketing Operations:

The Nework official community maintains, collects and sort out and handle feedbacks from users;

Online and offline NKC payment application scenarios is on schudle and small-scale testing has been conducted, test data is on analysis;

Preliminarily formulate the Nepica user invitation rules before going online, now has been completed by about 30%;

你可能感兴趣的:(Nework项目周报-(2018/04/02-2018/04/09))