2019-06-06 每日一题

A project management office (PMO) is presented with three project choices for
implementation.Project A has an internal rate of return (IRR) of 12%, project B has a schedule
performance index (SPI) of 0.8, and project C has a benefit-cost ratio (BCR) of 1:2.
Based on this information, which of the following projects should be pursued?
A. Project B
B. Projects C and B
C. Project A
D. Project C
项目管理办公室(PMO)有三个项目可供选择实施。项目A 的内部收益率(IRR)为12%,
项目B 的进度绩效指数(SPI)为0.8,项目C的效益-成本比(BCR)为1:2。根据这个信息,
应选择实施下列哪一个项目?
A.项目B
B.项目C和B
C.项目A
D.项目C
答案:C
解析:项目B进度延误,项目C的BCR小于1.推荐项目A,内部收益率通常与银行利率相比,高于当期利率即可选。