PMP模拟题(二)

共 200 题,时间240分钟,英文题目

1.In crashing a task, you would focus on:
A. As many tasks as possible
B. Non-critical tasks
C. Accelerating performance of tasks on critical path
D. Accelerate performance by minimizing cost
赶工一个任务时,你应该关注:
A 尽可能多的任务。
B 非关键任务。
C 加速执行关键路径上的任务。
D 通过成本最低化加速执行任务。
正确答案: C

2.‘I cannot test the software until I code the software.’ This expression describes
which of the following dependencies?
A. Discretionary
B. Soft
C. Preferential
D. Mandatory or hard
“在对软件编码前我不能进行软件测试。”这句话说明了哪种依赖关系?
A 随意的
B 软逻辑关系
C 优先
D 强制或硬逻辑关系
正确答案: D

3.Which of the following formulas provides the most accurate result for computing
activity duration?
A. AD = Work quantity / Production rate
B. AD = Work quantity / Number of resources
C. AD = Production rate / Work quantity
D. AD = (Production rate)(Work quantity) / Number of resources
以下哪个公式能最准确的计算活动历时?
A AD(活动历时)=工作数