Case 架构的实际应用-2

Test Plan in TestLink

1. For new release, we will create 2 test plans for each project

2. 1st test plan: New features in current release: this is used to do the first cycle new feature test before code freeze

3. 2nd test plan: All features in current release(including new features): this is used to do partial regression and full regression test

4. Build: Each test plan should have several builds to specify different iteration or phase

5. The tester must update the test status once the case is executed, if the case fails, the tester must fill ticket number in Description field, then we can pull the test report from Test Report-Query Matrix

6. For example:

Plan: 2013 Dec Release-New Features

Build: 1.0, 2.0

Plan: 2013 Dec Release-All Features

Build: 1.0, 2.0

 

你可能感兴趣的:(case)