Later, when unforeseen delays, interferences, shutdowns, change orders, work sequence changes, and a host of other noncontractor-caused problems are encountered, the effects of those unplanned, unforeseen events can be readily noted by adding them to the PDM schedule as they occur. An after-the-fact, actually performed schedule is called an as-built schedule.
As-built schedules, when compared to as-bid or as-planned schedules, provide what attorneys refer to as entitlement arguments, documented proof for the payment of monetary damages. Without any as-bid, as-planned, and as-built schedules, there are no entitlement proofs and, thus, there can be no damages due the contractor for hours, days, weeks, months, and even years wasted on what was perceived to be a clean, money-making project until all the problems began.
Schedules are not the only way to prove entitlements for damages, but they are miles ahead of whatever is in second place.